Cutover 

As we transition to Workday (HR, Payroll, and Finance), there will be deadlines for entering information in old systems such as PeopleSoft, MyAkron, and EmpCenter.  This page is where you’ll find the most up-to-date information about the transition.  Scroll down for timeline details, cutoff dates for specific activities, and an FAQ for further information. 

Workday Cutover Timeline

High-Level Dates 

Now – March 10:  All in-progress transactions should be completed in current systems.  Transactions prior to March 10 will be converted to Workday. 
 
March 11 – June 2: Only limited critical transactions for HR and Payroll will be processed in current systems.  These transactions will also be converted to Workday.  Please see the table below for details. 
 
April 5 – June 2: Only limited critical transactions for Finance will be processed in current systems.  These transactions will also be converted to Workday.  Please see table below for details. 
 
June 3 - June 4: No HR, Payroll, or Finance transactions will be allowed in current systems. 
 
June 5: Workday HR, Payroll, and Finance available for use University-wide. 

FAQ

Due to the nature of the migration from PeopleSoft/MyAkron and Empcenter to Workday, we are required to ‘freeze’ certain transactions to ensure a successful go live on June 5th.  Data for these transactions will be converted to Workday.  Unfortunately, we cannot just flip a switch to turn off the old systems and turn on Workday.  This process is called “cutover”.

As seen in the diagram above and the table below, freeze dates are transaction specific and represent the period of time when transactions are unavailable.  During the freeze period, the project team will be working to convert data from the old, legacy systems to Workday. 

Leave transactions will be tracked manually the week before go live, with the exception of users of the new time clocks.  The project team is looking at ways to facilitate the tracking of time during this week, but units should plan to track the time and prepare to enter it into Workday when the system opens up on June1st.

Critical HR transactions include: separations or unusual circumstances vetted through HR.

A critical transaction for Purchasing Services or Accounts Payable would include: 

  • A purchase and/or payment that is necessary for the protection of life or public safety, the protection of property, or the protection of other university assets. 
  • A purchase and/or payment that would halt critical university business or academic operations if not processed before the go-live date for Workday. 
  • A purchase and/or payment that that would result in loss of funding or not meeting obligations as set forth by the state or other regulatory bodies if not processed before the go-live date for Workday. 

Cutover Dates 

Details are subject to change as we continue to refine the cutover process. 
This table was last updated at 4:25pm on 4/25/2023. 

Work Area  Activity  Last Day for PeopleSoft/MyAkron Transactions  First Day for Workday Transactions  Notes  Communications 
All Request New Access to PeopleSoft HCM and Finance March 30th N/A
Finance Enter New Suppliers April 5th June 5th *Existing vendors must be used for goods and services between April 6th and June 5th
Finance Create New Speedtype or Amend Chartfields May 17th June 5th *Chartfield amendments done in Workday
Student Employment and Assistantships for graduate Students New hire requests and change requests with requested effective dates through May 7th Hire forms and change forms must be submitted by Friday, April 28th. N/A
Student Employment and Assistantships for graduate Students New hire requests and change requests with requested effective dates between May 8th and June 11th Hire forms and change forms must be submitted seven days in advance of the requested effective date (For ex: June 4th is last day to submit forms for June 11th requested effective date). N/A
Human Resources New Position Requests Unrelated to Search Waivers, Job Postings and Advertising May 17th June 5th

Purchasing Create a Requisition May 18th June 5th

*Pcard still available

Finance Travel Reimbursements, Check Requests, Invoices May 18th at 5pm June 5th *Full AP and Purchasing freeze between May 19th and June 5th
Finance Purchasing through ESM System May 31st June 5th
All PeopleSoft Access June 2nd June 5th
Human Resources Accept an Application and Search Waiver Approval June 2nd June 7th
Human Resources Close a Job Posting June 2nd June 7th

Human Resources Timeclock Usage  June 4th June 5th for webclocks and timeclocks *First shift on 6/5 will utilize new time clocks
Payroll  EmpCenter Transactions June 4th June 8th

*Time Off scheduled for after 6/5/23 will need to be re-entered into Workday

Payroll EmpCenter Approvals June 5th* June 5th** *Empcenter transactions through June 4th must be approved by June 5th.  This will be the last week to submit

timesheets in Empcenter.

**Approvals for transactions after June 5 will be done in Workday

Human Resources Approval for Job Candidate Offers June 20th* June 5th *Positions still open in PeopleSoft will be approved in PeopleSoft
Human Resources Hire a New Employee – June 26th* June 5th *Candidates for positions still open in PeopleSoft will be hired in PeopleSoft and migrated to Workday
Human Resources Download Search Materials  June 30th June 5th *Search Materials will not be converted to Workday 
Student Employment and Assistantships for graduate Students New hire requests and change requests with requested effective dates beginning June 12th N/A June 5th
Human Resources PAF Submission

May 9th: Bi-Weekly

May 22nd: Monthly

June 5th